Integrity Operating Window (IOW) Program Implementation Plan

Phase 1: Foundation (Months 0-6)
Initial Assessment & Planning
- Conduct gap analysis of existing monitoring systems
- Identify critical process units and damage mechanisms
- Form IOW implementation team
- Process engineers
- Integrity/materials engineers
- Operations representatives
- Inspection personnel
- Management sponsors
Priority Equipment Selection
- Crude unit
- Hydrotreater units
- FCC unit
- Sulfur recovery units
Key Parameters for Monitoring
- Temperature
- Pressure
- Flow rates
- pH
- Sulfur content
- TAN (Total Acid Number)
- Water content
- Chlorides
- H2S concentration
- NH3 levels
Phase 2: Development & Pilot (Months 6-12)
Establish IOW Limits
- Define four-tier system:
- Standard operating range
- Operation notification level
- Management notification level
- Shutdown criteria
Documentation Development
- Create IOW manual including:
- Parameter descriptions
- Measurement methods
- Response procedures
- Roles & responsibilities
- Review/update protocols
Pilot Program
- Implement on crude unit first
- Develop data collection systems
- Test notification protocols
- Refine procedures based on feedback
Phase 3: Full Implementation (Months 12-24)
Technology Infrastructure
- Install/upgrade monitoring systems
- Online analyzers
- Data historians
- Automated alerts
- Dashboard development
Training Program
- Operator training modules
- Engineer certification
- Management awareness sessions
- Contractor orientation
Roll-out Schedule
- Crude unit (Month 12-14)
- Hydrotreaters (Month 14-16)
- FCC unit (Month 16-18)
- Sulfur units (Month 18-20)
- Remaining units (Month 20-24)
Phase 4: Optimization & Sustainability (Ongoing)
Performance Metrics
- Track key indicators:
- Number of exceedances
- Response time to alerts
- Equipment reliability improvements
- Maintenance cost reduction
- Inspection findings correlation
Review & Update Process
- Monthly team meetings
- Quarterly management reviews
- Annual program assessment
- Three-year major review cycle
Continuous Improvement
- Regular parameter validation
- Update limits based on experience
- Incorporate new technology
- Add/modify parameters as needed
Southern Climate Considerations
Temperature Management
- Account for ambient temperature variations
- Consider humidity effects on equipment
- Plan for extreme weather events
- Hurricane preparedness integration
Corrosion Monitoring
- Enhanced focus on atmospheric corrosion
- CUI (Corrosion Under Insulation) program
- Moisture control strategies
- Materials selection guidelines
Success Factors
Critical Elements
- Management commitment
- Clear roles & responsibilities
- Effective communication protocols
- Robust data management
- Regular training & updates
- Integration with existing programs
- Process Safety Management (PSM)
- Mechanical Integrity
- Management of Change (MOC)
- Risk Based Inspection (RBI)
Key Performance Indicators
- IOW exceedance frequency
- Response time metrics
- Equipment reliability improvement
- Maintenance cost reduction
- Inspection finding correlation
- Training completion rates
Documentation & Records
Required Documentation
- IOW Manual
- Parameter basis documents
- Response procedures
- Training records
- Review meeting minutes
- Management reviews
- Incident investigations
- Change management records
Data Management
- Historian configuration
- Alert system setup
- Trending capabilities
- Report generation
- Data backup protocols